Pallara

ERCOT Large Load Readiness Register

What the public record establishes about named ERCOT large-load projects, and what it does not. Every value carries its source and the date it was retrieved. Nothing is inferred.

10 projects  ·  18 cited facts  ·  28 record statements  ·  55 open unknowns  ·  built 2026-08-16

Method

Public sources only. Company releases, official locations pages, ERCOT and PUCT records. No customer data and no confidential material.

Where a fact is absent from the reviewed sources it is published as an unknown. Absence is never filled by inference, and absence from the public record is not absence from an operator's files.

Capacity figures are labeled by measurement basis. Total power capacity, design capacity and approved interconnect capacity are distinct quantities and are not substitutes for aggregate peak Demand.

A statement published by a company is recorded as that company's statement, not as an independently verified ERCOT record.

Why this exists

On July 29, 2026 ERCOT presented preliminary Batch Zero eligibility to the Texas Senate Committee on Business and Commerce. The exclusions were documentation outcomes, not reliability findings.

Batch Zero preliminary eligibility, data as of July 28, 2026Projects
Not included — no qualifying study315
Not included — no dynamic model submitted by July 1047
Eligible for inclusion as allocated load127
Eligible, base or allocated load to be determined49
Eligible for inclusion as base load150
362 of 688 preliminarily excluded on documentation grounds. ERCOT's stated key takeaway on the same slide reads: “Approximately 205 GW of Large Load is eligible for inclusion in Batch Zero based on existing studies.” Only the project counts are reproduced here; the slide plots gigawatts in the same chart. Source: ERCOT, Assessing the Grid, Texas Senate Committee on Business and Commerce, July 29, 2026.

Not one of those exclusions is a reliability finding. They are missing documents. That is the failure mode this register tracks.

Projects

Cipher Colchis

Cipher Digital Inc. (NASDAQ: CIFR)  ·  BZ-01, BZ-04  ·  3 cited facts  ·  4 unknowns

Decision question Does the July 24 Batch Zero TSP-to-ERCOT submission deadline apply to Colchis — and if it does, which submissions remain open?

Cited public facts

Public record statements

Open unknowns — not established by any reviewed public source

CloudHQ SAT Campus

CloudHQ  ·  RT-02  ·  3 cited facts  ·  9 unknowns

Decision question Do the NOGRR282/NPRR1308 Large Computational Load ride-through requirements apply to SAT Campus, and which identity, site-boundary, Demand, exemption, interconnection, and evidence facts resolve the screen?

Cited public facts

Public record statements

Open unknowns — not established by any reviewed public source

Crusoe Stargate 1 Abilene

Crusoe  ·  RT-02  ·  3 cited facts  ·  4 unknowns

Decision question Do the NOGRR282/NPRR1308 Large Computational Load ride-through requirements apply to Stargate 1 Abilene, and which Crusoe or Lancium owner holds each required fact and record?

Cited public facts

Public record statements

Open unknowns — not established by any reviewed public source

Galaxy Helios

Galaxy Digital Inc. (NASDAQ: GLXY)  ·  RT-02  ·  1 cited fact  ·  5 unknowns

Decision question Do the NOGRR282/NPRR1308 Large Computational Load ride-through requirements apply to Helios, and which project facts and records resolve the screen?

Cited public facts

Public record statements

Open unknowns — not established by any reviewed public source

Rowan Temple

Rowan Digital Infrastructure  ·  BZ-01, BZ-04  ·  3 cited facts  ·  5 unknowns

Decision question Which of the three Batch Zero dates bind Temple — the July 24 TSP-to-ERCOT submission, the conditional August 1 Q1-2027 QSA prerequisite gate, and the currently unknown ERCOT classification date — and what must be true for each to matter? August 7 remains the adopted deadline ERCOT says it will miss; August 20 is only a PUCT process checkpoint.

Cited public facts

Public record statements

Open unknowns — not established by any reviewed public source

Sabey SDC Austin

Sabey Data Centers  ·  RT-02  ·  1 cited fact  ·  5 unknowns

Decision question Do the NOGRR282/NPRR1308 Large Computational Load ride-through requirements apply to SDC Austin, and which project facts and records resolve the screen?

Cited public facts

Public record statements

Open unknowns — not established by any reviewed public source

Satoshi Dragon Goby

Satoshi Energy  ·  RT-02  ·  1 cited fact  ·  7 unknowns

Decision question Do the NOGRR282/NPRR1308 Large Computational Load ride-through requirements apply to Dragon Goby, and which site-boundary, Demand, exemption, and evidence facts resolve the screen?

Cited public facts

Public record statements

Open unknowns — not established by any reviewed public source

Skybox PowerCampus Dallas

Skybox Datacenters  ·  RT-02  ·  1 cited fact  ·  4 unknowns

Decision question Do the NOGRR282/NPRR1308 Large Computational Load ride-through requirements (PUCT-approved 2026-07-09, effective 2026-08-01) apply to PowerCampus Dallas — and which project facts resolve the screen?

Cited public facts

Public record statements

Open unknowns — not established by any reviewed public source

STACK DFW02

STACK Infrastructure  ·  RT-02  ·  1 cited fact  ·  5 unknowns

Decision question Do the NOGRR282/NPRR1308 Large Computational Load ride-through requirements apply to DFW02, and which project facts and records resolve the screen?

Cited public facts

Public record statements

Open unknowns — not established by any reviewed public source

Tract Caldwell Valley

Tract  ·  RT-02  ·  1 cited fact  ·  7 unknowns

Decision question Do the NOGRR282/NPRR1308 Large Computational Load ride-through requirements apply to Caldwell Valley, and which site-boundary, Demand, exemption, and evidence facts resolve the screen?

Cited public facts

Public record statements

Open unknowns — not established by any reviewed public source

What this register does not do

It reports what the public record establishes. It does not say whether a project will energize on schedule, which entity holds a given compliance obligation, or what evidence would close a given gap. Those answers require the project's own records.

Pallara produces a fixed-scope Project Reality Screen for one named project: 72 hours, one fixed price, evidence-backed findings on project reality, energization, failure modes, operating constraints and financeability.